How to Install The Continuous Frying Machine?

Continuous Frying MachineBefore the normal operation of the fryer, we need to install the fryer. How to install the continuous frying machine? Today I will introduce you to the installation of  the continuous fryer machine.
1. First, we should connect the automatic temperature control meter box, blower, lifting motor, residue pump, the total power supply, check the fried baskets rise, down to be normal.
2. Then we should shut down the connection between the residue pump and the frying machine and start to rinse the fry, rust, rubbish and other debris in the fryer through the water in the fryer and release it through the man-made slag discharge port.
3. Then we need to install the oil pump and the connection line of the continuous frying machine, check the residue pump and the fryer all the pipes and joints do not leak oil, the slag filter wrapped in the slag filter bucket, and then placed Sheng Oil container. Use the residue pump to pump the oil in the oil container into the fryer (put the oil 15 cm away from the oil pan) and soak the thermocouple metal part of the meter in the oil.
4. Then we start to ignite, light coal with dry diesel light (using more than 7000 kcal anthracite), (350W-550W blower), we start small air volume combustion, oil temperature reached 165-180 ℃, the total amount of air blower Into the wind.
5. Finally, we need to check whether the electric metal part of the meter box is soaked in cooking oil, the temperature control display is normal, and the number in the temperature indication is switched to the temperature at which you need the pot.
This is the installation of the continuous frying machine,if you want to know more about the continuous fryer machine,just feel free to contact with me.
 

Leave Message For Price

*E-Mail
Tel
Country
*Message
*Code change